Dear friends, our architect Wojtek Kossowski send us a plan for works on both stupas during the summer. The plan is already approved by Sherab Gyaltsen Rinpoche. Please, find details below!
Krasnoyarsk
1st May
—
ground-breaking ceremony, Rinpoche will make pujas simultaneously in Kathmandu.
1-4 May
—
digging foundation pit and preparing formwork.
4-18 May
—
making concrete basement for the stupa.
18 May — 2 June
—
time needed for the concrete to dry.
3 June
—
Rinpoche arrives to Krasnoyarsk, starting the stupa filling. Simultaneously experts from “Supergranit” company (Poland) start mounting the granite elements of the stupa.
30 June
—
the stupa assembling is finished. Rinpoche continues rituals.
9 July
—
the stupa inauguration in Krasnoyarsk with Lama Ole and Sherab Gyaltsen Rinpoche.
Tankhoj
1 June
—
Sherab Gyaltsen Rinpoche makes the ground-breaking ceremony on the place of the stupa of Complete Victory. Then Rinpoche departs to Krasnoyarsk.
1-4 June
—
digging foundation pit and preparing formwork.
4-18 June
—
making concrete basement for the stupa.
18 June — 1 July
—
time needed for concrete to dry.
1-27 July
—
start of the granite Stupa elements assembling by experts from “Supergranit” company.
10 July
—
Rinpoche returns to Tankhoj, beginning of the Stupa filling.
12-16 July
—
course in Ulan-Ude with Lama Ole and Sherab Gyaltsen Rinpoche. Rinpoche presents on the course 15-16 July.
27 July
—
Inauguration of the Stupa of Complete Victory on Baikal with Lama Ole and Sherab Gyaltsen Rinpoche.
We are getting many letters from friends offering their physical participation in the stupas construction. We are very inspired by your wish to help, and also gratitude for that! However, as you can see from the schedule above, all physical resources demanding works on ground and concrete must be finished by 18 May in Krasnoyarsk and by 18 June in Tankhoj. After that all work on the stupas construction will be done by experts from “Supergranit” company, which do not need help. So, during Rinpoche presence at the construction sites there will be no possibility to contribute to the stupas construction directly.
We are working now on more detailed work schedule and a list of vacancies for different periods of construction. Soon, we will publish it on this site or in news mailing list, so those who wants can find place and time where their participation would be most needed! For example, large amount of work related to the stupas filling preparation must be finished by 1 June.
More details about accommodation options and meals during the summer program will appear soon as well.